The contract is signed with 23rd Regional Directorate of State Hydraulic Works on 12th Aug 2015, aims to relocate the existing water supply line that would otherwise be left within the reservoir area of Bartın Kirazlıköprü Dam once completed.

Project consists of relocation of approximately 7.9 km of transmission line to be constructed with steel pipes to supply water to Bartın city center.

PROJECT DETAILS
  • Client : 23rd Directorate of State Hydraulic Works
  • Project Name : Kirazlıköprü Potable water line relocation and installation of service road railings and slope stabilization works
  • Contract Date : 12.08.2015
  • Completion Date as Stated on the Contract : 13.11.2016